Bulk Operation

  1. Choose Issues
  2. Choose Operation
  3. Operation Details
  4. Confirmation

Step 1 of 4: Choose Issues

Cancel

T Key Summary Assignee Reporter P Status Resolution Created Updated Due Σ Progress Development
Sub-task POULPE-118

POULPE-101 Writing Test Cases

Pavel Vervenko Pavel Vervenko Major Closed Fixed 17/Dec/11

66%

Original Estimate - 3h
Time Spent - 2h Remaining Estimate - 1h
Sub-task POULPE-105

POULPE-101 Managing Ranks. Rank Editor

Pavel Vervenko Pavel Vervenko Major Closed Fixed  

40%

Original Estimate - 15h
Time Spent - 6h Remaining Estimate - 9h
Sub-task POULPE-104

POULPE-101 Managing Ranks. Ransk page

Pavel Vervenko Pavel Vervenko Major Closed Fixed  

62%

Original Estimate - 16h
Time Spent - 10h Remaining Estimate - 6h
Sub-task POULPE-103

POULPE-101 Managing Ranks. Services Layer

Pavel Vervenko Pavel Vervenko Major Closed Fixed  

12%

Original Estimate - 8h
Time Spent - 1h Remaining Estimate - 7h
Sub-task POULPE-102

POULPE-101 Managing Ranks. Model Layer

Pavel Vervenko Pavel Vervenko Major Closed Fixed  

25%

Original Estimate - 10h
Time Spent - 2.5h Remaining Estimate - 7.5h

Cancel